The following is the latest update regarding the road construction happening in Oneida:

Ranch Road

  • All driveway tie ins are complete. Intersections are also complete with the exception of Evergreen Dr, Deer Path, and Park Dr.
  • Shouldering , restoration, and guard rail upgrades to follow once all paving is complete.

Old Seymour Road

  • No work on Old Seymour Rd this week as of this morning. The county worked on paving on Seminary Rd and Ranch Rd.
  • Intersection and driveway paving to take place over the next week or two.
  • Shouldering , restoration, and guard rail upgrades to follow once paving is complete.

Seminary Road

  • Mainline surface paving is complete.
  • The county started intersection and driveway tie in paving, beginning at CTH E and working to the north. Paving work should be complete in the next week or so.
  • Shouldering , restoration, guard rail upgrades, and striping to follow once paving is complete.