The following is the latest update regarding the road construction happening in Oneida:
Ranch Road
- All driveway tie ins are complete. Intersections are also complete with the exception of Evergreen Dr, Deer Path, and Park Dr.
- Shouldering , restoration, and guard rail upgrades to follow once all paving is complete.
Old Seymour Road
- No work on Old Seymour Rd this week as of this morning. The county worked on paving on Seminary Rd and Ranch Rd.
- Intersection and driveway paving to take place over the next week or two.
- Shouldering , restoration, and guard rail upgrades to follow once paving is complete.
Seminary Road
- Mainline surface paving is complete.
- The county started intersection and driveway tie in paving, beginning at CTH E and working to the north. Paving work should be complete in the next week or so.
- Shouldering , restoration, guard rail upgrades, and striping to follow once paving is complete.
FY27 Community Budget Meetings for SEOTS and Oneida Casino Hotel. Email malvarad@oneidanation.org with questions.


A Share Back Event is being held this week at North Star Casino for Wisconsin Tribes relating to wellness and recovery:

Oneida Land Claims book Club meetings:

Skaˀnikú·lat is seeking a Communications Support & Community Outreach Intern. Check out the link for more information about this internship: https://docs.google.com/document/d/1TNNqsJNFeaPQrW3SPWsDBLWrU4Zc-2axMa0GGTWMCv4/edit?usp=sharing

Youth Flag Football Event will take place on Fridays from July 31st through August 28th (please see flyer for more details).