24-102 Casino Grill Remodel

…equipment Current Status: Engineering and Gaming have been working through various internal approvals. Design documents are complete. Construction activities are scheduled to commence July 9th. Schedule: Approvals – On-Going Design

https://oneida-nsn.gov/wp-content/uploads/2024/07/24-102-Casino-Grill-Remodel.pdf?_rt=NjExfDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=c17a894098

21-114 Sacred Burial Grounds Expansion

…of the parcel will be used. Current Status:  OES completed concept design (see page 2).  The proposed layout includes 3,780 new plots.  Client (Land Management) sent out…

https://oneida-nsn.gov/wp-content/uploads/2023/12/21-114-Sacred-Burial-Grounds-Expansion-1.pdf?_rt=NjEyfDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=f1c1d7dc76

21-111 Multi-Family Housing

…by Comprehensive Housing Division. Current Status:  Architectural and site design are progressing.  Weekly design update/review meetings are being held. Schedule: Approvals – complete 7/27/22 Design – finished in…

https://oneida-nsn.gov/wp-content/uploads/2023/12/21-111-Multi-Family-Housing-1.pdf?_rt=NjEzfDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=ef0a17c052

21-105 Orchard Buildings

…Mission Support Services, LLC for Design-Build services. Schedule: Approvals – In Process Bidding– TBD Design – TBD Construction – TBD Project Partners: Engineering, Orchard, Land, Comprehensive Housing, Purchasing, Legal Office….

https://oneida-nsn.gov/wp-content/uploads/2023/12/21-105-Orchard-Buildings-1.pdf?_rt=NjE0fDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=780455290c

22-105 Mission Park Renovations

design services and prepare construction costs. Current Status: OES presented various design concepts and solutions to resolve the stormwater issues to the project team. The project client had determined that…

https://oneida-nsn.gov/wp-content/uploads/2023/03/22-105-Mission-Park-Renovations.pdf?_rt=NjE1fDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=1325d9a914

23-111 Skenandoah Complex Lobby Renovation

…for Design-Build services. Current Status: The AIA Design-Build agreement is currently being drafted for review and will be routed through the approval process. Schedule: Approvals – Complete Design – TBD…

https://oneida-nsn.gov/wp-content/uploads/2024/02/23-111-Skenandoah-Complex-Lobby-Renovation.pdf?_rt=NjE2fDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=caffa05188

22-105 Mission Park Renovations

design services and prepare construction costs. Current Status: OES presented various design concepts and estimated cost to the project team. The team is currently reviewing the presented options and associated…

https://oneida-nsn.gov/wp-content/uploads/2022/11/22-105-Mission-Park-Renovations.pdf?_rt=NjE3fDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=8f44998592

21-104 Gaming Commission Relocation

…. Current Status: • Design-build contract with MS2 for project. • Seven Generations Architects and Engineers targeting Issuing Final Design Documents for the Project by end of December. Schedule: Approvals…

https://oneida-nsn.gov/wp-content/uploads/2022/12/21-104-Gaming-Commission-Relocation.pdf?_rt=NjE4fDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=5c3dd53078

19-002 E&EE One Stop Replacement

…will maximize profitability at this location. The Oneida Engineering Department executed a Design-Build agreement with Mission Support Services, LLC. Current Status: The project is currently in the Schematic Design phase….

https://oneida-nsn.gov/wp-content/uploads/2023/10/19-002-EEE-One-Stop-Replacement.pdf?_rt=NjE5fDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=256ba2e616

21-105 Orchard Buildings

…the current site. Per OBC Resolution #04-08-20-K, the Engineering Department will be contracting with Mission Support Services, LLC for Design-Build services. Current Status: Continuing with Design Development for the Retail…

https://oneida-nsn.gov/wp-content/uploads/2024/06/21-105-Orchard-Buildings.pdf?_rt=NjIwfDYyfNC00LjQt9Cw0LnQvSDRh9C10LvQvtCy0LXQutCwINCy0LjQutGC0L7RgNC40Y8g0LTQttC10Lwg0YLQvtC_0L7QstGL0Lkg0YHQv9C10YbQuNCw0LvQuNGB0YIg0LTQuNC30LDQudC9INGH0LXQu9C-0LLQtdC60LAgaHVtYW4gZGVzaWduIG1ldGFoZC5ydXwxNzIwMzg3NDQ3&_rt_nonce=ef6e8b63d2